Lecture Project management: A managerial approach – Chapter 10: Monitoring and information systems

33 95 0
Lecture Project management: A managerial approach – Chapter 10: Monitoring and information systems

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

Thông tin tài liệu

Chapter 10 examines the information requirements of a project and the need for monitoring critical activities. Included in this chapter is a description of some common project management information systems (PMIS).

Chapter 10 Monitoring and  Information  Systems Copyright 2015 John Wiley & Sons, Inc Terms  Monitoring ­ Collecting, recording, and  reporting information concerning any and  all aspects of project performance  Controlling ­ Uses the data supplied by  monitoring to bring actual performance  into compliance with the plan  Evaluation ­ Judgments regarding the  quality and effectiveness of project  performance 10­2 The Planning–Monitoring–Controlling  Cycle  We mainly want to monitor: – – – Time (schedule) Cost (budget) Scope (project performance)  Closed­loop system – Revised plans and schedules following  corrective actions 10­3 Project Authorization and Expenditure  Control System Information Flow 10­4 Designing the Monitoring System Identify key factors to be controlled  – – –  Scope Cost Time Information to be collected must be  identified 10­5 Designing the Monitoring System  Continued  Do not want to avoid collecting necessary  data because it is hard to get  Do not want to collect too much data  The next step is to design a reporting  system that gets the data to the proper  people in a timely and understandable  manner 10­6 Five Telltale Signs of Project Trouble  Muddy waters  Mysterious stakeholders  Unconstrained constraints  Suspicious status reports  Discord and drama 10­7 Data Collection  Once we know the data we want, we  need to decide how to collect it  Should the data be collected after some  event?  Should it be collected on a regular basis?  Are there any special forms needed for  data collection? 10­8 Forms of Data      Frequency counts Raw numbers Subjective numeric ratings Indicators Verbal measures 10­9 Information Needs and Reporting  Everyone should be tied into the reporting  system  Reports should address each level  Not at same depth and frequency for  every level – – Lower­level needs detailed information Senior management levels need overview  reports  Report frequency is typically high at low  levels and less frequent at higher levels 10­10 Rules to Aid in Estimating Percent  Completion  50­50 rule  0­100 percent rule  Critical input use rule  Proportionality rule 10­19 The Earned Value Chart 10­20 Variances  Variances can help analyze a project  A negative variance is bad Cost and schedule variances are calculated  as the earned value minus some other  measure Will look at some of the more common  ones 10­21 Cost Variance (CV)  CV = EV – AC  Negative variance indicates a cost  overrun  Magnitude depends on the costs 10­22 Schedule Variance (SV)  SV = EV – PV  Negative variance indicates you are  behind schedule  Measured using costs 10­23 Time Variance (TV)  TV = ST – AT  Negative variance indicates you are  behind schedule 10­24 Indices  Cost Performance Index  CPI = EV/AC  Schedule Performance Index  SPI = EV/PV  Time Performance Index  TPI = ST/AT   Cost Schedule Index  CSI = EV2/(AC)(PV) 10­25 “To complete” and “At Completion”  Project manager reviewing what is  complete and what remains  Final cost and final completion date are  moving targets  The project manager compiles these into  a to complete forecast  Actual + forecast = final date and cost at  completion 10­26 ETC and EAC ETC = (BAC + EV)/CPI EAC = ETC + AC where, ETC = Estimated cost to complete BAC = Budget at completion EV    = Earned value CPI   = Cost performance index EAC  = Estimated cost at completion AC    = Amount expended to date (actual cost) 10­27 Milestone Reporting  Reports that are created when a project  reaches a major milestone  They are designed to keep everyone up­ to­date on project status  For executives and clients, these may be  the only reports they receive 10­28 Burnup and Burndown Charts  Especially popular with agile development  For monitoring and communicating  overall project progress.   Scope is on the vertical axis  Time is on the horizontal axis 10­29 Burnup and Burndown Charts  Burndown charts:  – The remaining work to be completed it  included  Burnup charts:  – Include two plotted lines Amount of work completed to date Total amount of work to be completed 10­30 Computerized PMIS (Project  Management Information Systems)  Real projects are often large – – Hundreds of tasks Thousands of work units  Reporting is clearly a job for the computer  Project management information systems  were one of the earlier applications  Initially focus was on scheduling  Now it includes, earned values,  variances, and more 10­31 PMIS Errors  Managing the PMIS  Computer paralysis  PMIS verification  Information overload  Project isolation  Computer dependence  PMIS misdirection 10­32 PMIS Desirable Attributes  Friendliness  Graphics  Schedules  Charts  Calendars  Migration  Budgets  Consolidation  Reports  Access 10­33 ... One way is by using an aggregate  performance measure called earned  value 10­17 The Earned Value Chart and Calculations  Actual against baseline ignores the  amount of work accomplished  Earned value incorporates work ... Variances can help analyze a project  A negative variance is bad Cost and schedule variances are calculated  as the earned value minus some other  measure Will look at some of the more common  ones 10­21 Cost Variance (CV)... Final cost and final completion date are  moving targets  The project manager compiles these into  a to complete forecast  Actual + forecast = final date and cost at  completion 10­26 ETC and EAC ETC = (BAC + EV)/CPI EAC = ETC + AC

Ngày đăng: 16/01/2020, 09:01

Từ khóa liên quan

Mục lục

  • Chapter 10

  • Terms

  • The Planning–Monitoring–Controlling Cycle

  • Project Authorization and Expenditure Control System Information Flow

  • Designing the Monitoring System

  • Designing the Monitoring System Continued

  • Five Telltale Signs of Project Trouble

  • Data Collection

  • Forms of Data

  • Information Needs and Reporting

  • The Reporting Process

  • Benefits of Detailed and Timely Reports

  • Report Types

  • Meetings

  • Meeting Rules

  • Common Reporting Problems

  • Earned Value Analysis

  • The Earned Value Chart and Calculations

  • Rules to Aid in Estimating Percent Completion

  • The Earned Value Chart

Tài liệu cùng người dùng

  • Đang cập nhật ...

Tài liệu liên quan